Construction Updates


collage of road construction pictures

Gov Delivery LetterSubscribe to ALL Ramsey County Construction Updates

 CLICK HERE to view a map of the 2014 Construction Projects

Countywide Bituminous Mill & Overlay Project

The Ramsey County Board of Commissioners authorized a $10 wheelage tax, beginning this year, for all vehicles registered in Ramsey County.  The County anticipates that the wheelage tax will generate $3.8 million which will go directly to the resurfacing of roadways.  The following projects are a result of the wheelage tax for the 2014 construction season.  The projects include removal and replacement of concrete pedestrian ramps, spot repairs of curb and gutter, and milling and overlaying the top surface of the roadway.

 

Ramsey County in cooperation with the Cities of Arden Hills, Shoreview, Roseville, St. Paul, Maplewood, St. Anthony Village, Vadnias Heights, and Little Canada is planning the bituminous mill and overlay of several concrete County roadways in the construction season of 2014. (MAP)  The following segments of roadway are proposed to be mill and overlayed:

  • Warner Road (CSAH 36) [End of concrete to 680’ east of TH # 61] - Anticipated Completion  July 2014
  • Jackson Street (CSAH 55) [Acker Street to Maryland Avenue] - Start Date July 10, 2014 -  August  2014
  • Lexington Avenue (CSAH 51) [University Avenue to Orchard Avenue] - Start Date July 14, 2014 -  August  2014
  • Marshall Avenue (CSAH 35) [Snelling Avenue to Lexington Avenue] - Start Date July 14, 2014 -  August  2014
  • Edgecombe Road  (CSAH 46) [T. H. 5 to St. Paul Road] - Anticipated Start Date July 21, 2014 -  August  2014
  • Hodgson Road (CSAH 49) [North Birch Lane to County Road I] - Anticipated Start Date Fall 2014 - November 2014
  • White Bear Avenue (CSAH 65) [Cope to 11th Street] - Anticipated Start Date Fall 2014 - November 2014
  • County Road B2 (CSAH 78) [Cleveland Avenue to Fairview Avenue] - Anticipated Start Date Fall 2014 - November 2014
  • County Road C (CSAH 23) [Rice Street to Little Canada Road] - Anticipated Start Date Fall 2014 - November 2014
  • County Road C (CSAH 23) [Highway 88 to Long Lake Road] - Anticipated Start Date Fall 2014 - November 2014
  • Dale Street (CSAH 53) [Arlington Street to Larpenteur Avenue] - Anticipated Start Date Fall 2014 - November 2014
  • Labore  Road  (CSAH 108) [I694 to County Road E] - Anticipated Start Date Fall 2014 - November 2014
  • Johnson Parkway  (CSAH 64) [Minnehaha Avenue to Phalen Blvd.] - Anticipated Start Date Fall 2014 - November 2014
  • Hodgson Road (CSAH 49) [County Road I to County Road J] - Anticipated Start Date Fall 2014 - November 2014
  • Hamline Avenue (CSAH 50) [Floral Drive to CSAH 96] - Anticipated Start Date Fall 2014 - November 2014
  • Larpenteur Avenue (CSAH 30) [Rice Street to Jackson Street] - Anticipated Start Date Fall 2014 - November 2014

The contractor, Bituminous Roadways, is scheduled to start construction July 2014.  Motorists should expect that each of the sixteen roadway segments will have lane restrictions and turning movement restrictions during the work on the specific intersections.  The County will provide project updates regarding the specific project and phase of the project posted on our website.  The dates provided for each of the phases are subject to weather delays.

 

The Contractor anticipates having the roadway construction completed by November 2014.

 

The County will update the website every two weeks or as needed for the projects.  The County will send out e-mails to all the subscribers for the project. (Sign up for Construction Updates)

If you have any questions about the construction project, contact Brian Essler, project supervisor, at 651-248-0175 or brian.essler@co.ramsey.mn.us; Rob Gaetz at 651-558-8495, or Jerry Auge, Jr. at 651-266-7117.


**7/15/2014 Update**

Warner Road is paved and striped. The traffic control has been taken down for the mill and overlay portion of the project.

 

New pedestrian ramps are being installed on Jackson Street. If weather permits, the contractor will mill the road on Monday, July 21st. The plan for the rest of the week is: install the loops, raise the gate valves, and pave.

 

The contractor is removing and installing new pedestrian ramps on Lexington Avenue and Marshall Avenue.

 

Marshall Avenue will be closed for the removal of the rail road tracks on July 22nd and 23rd .

 

The contractor plans to begin work on Edgecombe Road on Monday, July 21st.

 

If you have any questions about the construction project, contact Brian Essler, project supervisor, at 651-248-0175 or via brian.essler@co.ramsey.mn.us; Rob Gaetz at 651-558-8495, or Jerry Auge, Jr. at 651-266-7117.


**END OF UPDATE**


Countywide Concrete Rehabilitation Project

Ramsey County in cooperation with the Cities of Arden Hills, Shoreview, Roseville, St. Paul, Maplewood, North Oaks, White Bear Lake, and White Bear Township is planning the rehabilitation of several concrete County roadways in the construction seasons of 2014 and 2015. (Map)  The following segments of roadway are proposed to be rehabilitated:

  • Larpenteur Avenue (CSAH 30) [Fernwood Street to Dale Street] - Anticipated Completion  July 2014
  • County Highway 96 (CSAH 96) [US 10 to Centerville Road] - Start Date June 9, 2014 -  August  2014
  • White Bear Avenue (CSAH 65) [County Road F to HWY 61] - Anticipated Start Date August 2014 - September 2014
  • Parkway Drive (CSAH 27) [Larpenteur Avenue and 700’ North of Larpenteur Avenue] - Anticipated Completion July 2014

Gov Delivery Letter Subscribe to concrete rehab e-mail updates

The contractor, Interstate Improvement, Inc., is scheduled to start construction May 2014.  Motorists should expect that each of the four roadway segments will have lane restrictions and turning movement restrictions during the work on the specific intersections.  The County will provide project updates regarding the specific project and phase of the project posted on our website.  The dates provided for each of the phases are subject to weather delays.

The Contractor anticipates having the roadway construction completed by August 2014.

The County will update the website every two weeks or as needed for the projects.  The County will send out e-mails to all the subscribers for the project. (Sign up for updates)

If you have any questions about the construction project, contact Brian Essler, project supervisor, at 651-248-0175 or brian.essler@co.ramsey.mn.us; Daniel Bodelson at 651-248-0173, or Jerry Auge, Jr. at 651-266-7117.


**7/29/2014 Concrete Rehabilitation Update**

The traffic on Larpenteur Avenue continues to be reduced to one lane in each direction.  Ti Zak will be installing the curb, sidewalk and median noses this week.  Bituminous Roadways will patching in at the ends of the concrete pavement. The work at Dale Street is taking longer than anticipated.  In order to finish the Dale Street signal system, Xcel Energy needed to relocate the existing utility pole on the southwest corner of the intersection.  Delays from Xcel Energy are a result of the flooding and storms that hit the metro area in mid June.  During this time the intersection of Dale Street and Larpenteur Avenue will remain in a four way stop situation.  Other utility relocations in this area have already been completed.  Victoria Intersection will remain in a three way stop situation until the signal power is provided.

Parkway Drive is reduced to one lane in both directions.   Larpenteur Avenue east of Parkway Drive has been reopened to traffic.  Collins Electric is installing the new signal systems at Parkway Drive & Larpenteur Avenue.  Traffic at Parkway and Larpenteur intersection is being controlled with a three-way stop situation. 
 
County Highway 96 is a roadway that is in overall great condition with some minor deterioration.  While in the corridor the County is repairing deteriorated concrete crosswalks and minor pavement distresses from US Highway 10 to I-35E.  The colored concrete cross walks have been rapidly deteriorating over the past couple of years.  The crosswalks are being replaced with regular colored concrete.  Addressing minor pavement distresses at this time will prevent larger distresses from occurring in the near future.  County Highway 96 is currently reduced to one lane in each direction from Dale Street to Centerville Road. This will continue throughout this phase the concrete rehabilitation project.  A traffic change is scheduled for Wednesday, July 30th, for moving motorists on 96 to the outside lanes.  Motorists should expect this phase of the rehab to continue into the week of Aug 11th.
 
The work on White Bear Avenue from US 61 to County Road F is scheduled to begin on Aug. 4th.
If you have any questions about the construction project, contact Brian Essler, project supervisor, at 651-248-0175 or via brian.essler@co.ramsey.mn.us; Daniel Bodelson at 651-248-0173, or Jerry Auge, Jr. at 651-266-7117.

**END OF UPDATE**

Maryland and Payne Avenue Project

Gov Delivery LetterSubscribe to Maryland and Payne Avenue project e-mail updates

Ramsey County, in cooperation with the City of St. Paul, is planning the reconstruction of Maryland Avenue from Greenbrier Street to Edgerton Street.  The purpose of the project is to add left turn lanes on Maryland Avenue at Payne Avenue. This project will widen the roadway and includes new traffic signal system to allow for protected left turns (green turn arrow) at Payne Avenue intersection. Sidewalks will be reconstructed to meet Americans with Disability Act standards.   Ramsey County has bid the project and is planned for construction to start the week of July 14, 2014. (View project layout)

The Project has four distinct phases:

Phase I will consist of removing buildings along the corridor, installing temporary water mains for properties and businesses between Edgerton and Greenbrier Street. Utility relocations by Xcel Energy and Century Link will occur during this phase. Limited daily lane closures are necessary for this phase of the project. This phase is scheduled to start July 14, 2014 to July 28, 2014.

Phase II will include closing of the roadway from Edgerton Street to Payne Avenue to install new water main and storm sewer, repair the existing sanitary sewer, and excavate and construct the roadway with bituminous and concrete curb and gutter between those blocks. The existing signals at the intersection of Payne Avenue will be removed. This phase is estimated to start July 28, 2014 to August 31, 2014.

Phase III will include closing the intersection of Payne Avenue and Maryland Avenue to reconstruct the intersection and install utilities throughout the intersection. This phase is scheduled to start August, 18, 2014 to August 30, 2014.

Phase IV will include closing the roadway from Payne Avenue to Greenbrier Street to install new water main and storm sewer, repair the existing sanitary sewer, and excavate and construct the roadway with bituminous and concrete curb and gutter between those blocks. This phase is estimated to begin September 1, 2014 to October 6, 2014.

Once all of the curb and gutter is placed and two layers of bituminous pavement is installed, the County will close the entire section of the project to put a final bituminous pavement layer down to complete the project.

For questions please call Randy Bussierre at 651-248-4076, Bret Wieman at 651-248-0027 or Jerry Auge at 651-266-7117.  


Warner Road Bridge Reconstruction Project

Ramsey County, in cooperation with the City of St. Paul, is reconstructing the eastbound Warner Road Bridge over Childs Road with grade separated trail crossing at both the east and west end of the bridge. View PROJECT LAYOUT. Construction is underway and is planned to last 2 years with completion in October 2015. Traffic will remain shifted to the westbound bridge to allow for one lane of traffic in each direction for the duration of the project. The trail will be closed over Warner Bridge as well. A trail detour is in place that routes users through downtown St Paul and Indian Mounds Park. View Detour Route

Please contact Project Manager, Erin Laberee at erin.laberee@co.ramsey.mn.us or 651-266-7105 with questions.

Gov Delivery Letter E-Subscribe to  Construction Updates


Centerville Road Resurfacing Project

Ramsey County maintenance staff will be conducting a roadway resurfacing project on Centerville Road from County Road H2 to County Road J in North Oaks/White Bear Township. This project will consist of the milling and combining of the roadway surface and base(reclamation), removal of excess material to accommodate new bituminous surface, roadway grading, and paving of a new roadway surface.  This work is anticipated to start on June 18, 2014, and be completed the week of July 7, 2014 (weather permitting).  During this work, the roadway will be closed to through traffic. (CLICK HERE FOR DETOUR MAP) Localized traffic will be directed through the work zone and access will be maintained to all residents and businesses during construction.

Anticipated project schedule:
• Milling and combining of bituminous pavement and base – June 18 - June 19
• Grading of roadway and removal of excess material – June 23 – June 27
• Bituminous paving – week of June 30 and July 7th
• Pavement markings - week of July 14th

Motorists are encouraged to use the posted detour route and any alternate accesses during construction.
If you have any questions, please contact Ryan Smith at 651-266-7194, Mark Rauchbauer at 651-266-7193, or Jerry Auge at 651-266-7117.


Buffalo Street Resurfacing Project

Ramsey County maintenance staff will be conducting a roadway resurfacing project on Buffalo Street from US Highway 61 to Portland Avenue in White Bear Lake. This project will consist of the milling and combining of the roadway surface and base (reclamation), removal of excess material to accommodate new bituminous surface, roadway grading, and paving of a new roadway surface.  This work is anticipated to start on August 11, 2014 and completed the week of August 18, 2014. During this work, the roadway will be closed to through traffic. Localized traffic will be directed through the work zone and access will be maintained to all residents and businesses during construction.

Motorists are encouraged to use the posted detour route and any alternate accesses during construction.
If you have any questions, please contact Ryan Smith at 651-266-7194, Mark Rauchbauer at 651-266-7193, or Jerry Auge at 651-266-7117.


County Road C Resurfacing Project

Ramsey County maintenance staff will be conducting a roadway resurfacing project on County Road C from US Highway 61 to Keller Parkway in Maplewood. This project will consist of the milling and combining of the roadway surface and base (reclamation), removal of excess material to accommodate new bituminous surface, roadway grading, and paving of a new roadway surface. Ditch regarding and culvert repair work will also be conducted prior to roadway paving. This work is anticipated to start on July 21, 2014 and be completed the week of August 4, 2014.  During this work the roadway will be closed to through traffic. Localized traffic will be directed through the work zone and access will be maintained to all residents and businesses during construction.

Motorists are encouraged to use the posted detour route and any alternate accesses during construction.

If you have any questions, please contact Chuck Markham at 651-266-7196, Mark Rauchbauer at 651-266-7193, or Jerry Auge at 651-266-7117.


Highway 96/US 10 Grade Separation

Ramsey County, the Minnesota Department of Transportation, the City of Arden Hills and surrounding communities have been working on a solution for the Highway 96/US Highway 10 intersection for several years. The construction contract with Shafer Contracting is being administered by MnDOT. Construction is underway and scheduled to be complete in July 2014.  CLICK HERE to view a layout of this project.

For questions call Beth Engum, Project Manager at 651-266-7115 or CLICK HERE to visit MnDOT's website.

A noise wall is proposed for the north side of Highway 96 along the Arden Manor Mobile Home Park. CLICK HERE for more information regarding the noise wall analysis and design.


For Current Road Construction and Traffic Updates, go to: